Town Edson 51St Street Storm Sewer Replacement
The Town tendered the replacement of a section of collapsed and damaged storm piping on 51 Street in Edson, which straddles the east and westbound lanes of the Yellowhead Highway (Hwy 16). Due to year-end financial constraints, Option collaborated with the Town to adjust the project scope and find cost saving alternatives to reduce the project budget by $112,000 - a further $30,0000 of savings were found during construction to assist the Town and successfully deliver it under budget. Construction particulars included
- Project start up activities; contract execution, submittals (ECO/ESC Plan, TAS, Schedule, Shop Drawings), and procurement
- Traffic accommodation measures addressing heavy volume traffic on Hwy 16
- New storm sewer installation of 600mm CL4 (96m), 1500mm manholes (2), 900mm catch basins (3) and connection leads to the existing infrastructure
- New wheelchair/bike ramps and the restoration of 40m of curb and gutter
- Restoration of 1300m2 of asphalt
- Site restoration